Release Status

Released.

Last updated: 2 March 2011.

Release Schedule

Action Expected Actual Publicly Announced
Initial release schedule announcement - 2010-10-08 2010-10-22
Release schedule reminder - 2010-11-01,2010-11-15,2010-11-28 2010-11-22
Code Freeze 2010-11-28 2010-11-29 -
BETA1 2010-12-03 2010-12-04/05 2010-12-10
Doc tree schedule announcement - - 2010-12-20
Doc tree slush 2010-12-23 2010-12-23 2010-12-23
Doc tree tag 2011-01-10 2011-01-10 2011-01-10
Ports tree schedule announcement - - 2010-12-07
Ports tree feature freeze 2011-01-07 2011-01-11 2011-01-11
RC1 2010-12-17 2010-12-22 2010-12-27
stable/8 opened again 2010-12-20 2010-12-26 2010-12-27
RC2 2011-01-07 2011-01-12 2011-01-16
RC3 (-) 2011-01-28 2011-01-29/30 2011-02-03
RELEASE build 2011-01-21 2011-02-16/17 -
RELEASE announcement 2011-01-24 - 2011-02-24

CAUTION: FreeBSD Release Schedules may slip so the above dates are not guaranteed.

Branch status

Action Status
Subversion: releng/8.2 created DONE 20101221, r216618
Subversion: release/8.2.0 created DONE 20110216, r218742
CVS: RELENG_8_2_BP created DONE 20101221
CVS: RELENG_8_2 created DONE 20101221
CVS: RELENG_8_2_0_RELEASE created DONE 20110216
CVS: ports tree tagged DONE 20110208
Tinderbox: RELENG_8_2 configured DONE 20101227

Change approval and merge guidelines

Read ChangeRequestGuidelines carefully. All requests neglecting these rules will be rejected.

Release engineering issue and patch queue

The being-fixed and still-being-researched pile

Blanket approvals

The following blanket approvals are valid until BETA1:

The waiting for approval pile

The additional review or revisions sought pile

The approved and queued for commit pile

Committed fix pile

During BETA1:

After BETA1:

After branching to stable/8 and releng/8.2:

To releng/8.2 after stable/8 branch opened again:

To releng/8.2 after RC2:

To releng/8.2 after RC3:

The change request withdrawn pile

Rejected change request pile

Unauthorized commits

Likely errata items

Leading up to the release

Projects being worked on before code freeze

Project Developer Status
Xen bugfixes ColinPercival Ongoing

Projects being worked on after code freeze

Project Developer Status
bind security update DougBarton Done
openssl security update SimonNielsen Done

Known issues when the release process started